Eddystone and Daubeney Towers gas supply
Daubeney and Eddystone are 26-storey residential blocks on the Pepys Estate in Deptford, each containing 145 flats.
SGN intends to shut off Daubeney Tower’s gas supply on or before 31 March 2027. At Eddystone Tower, the supply may continue for a limited period beyond March – but this has not been formally confirmed.
Ourfirst priority is safety, followed by enabling residents to stay comfortably at home.
Based on the current safety position, residents can remain in their homes and use heating, hot water and cooking facilities as normal. SGN continues regular safety checks. Residents will be contacted directly if this changes and should not arrange changes to their equipment themselves.
Officers are working at pace to ensure alternative provision for utilities once the SGN supply comes to an end. At present, two main options are being assessed: new communal gas heating and hot water systems (with a central boiler providing hot water across each building); or electric heating and hot water in individual homes. No final decision has been made.
Contingency plans are also being drawn up, should the new provision not be in place by March. They include temporary heating, hot water and cooking facilities, although some households may need to move temporarily, depending on safety assessments and individual needs.
We are keen to limit impacts to residents as far as possible. Arrangements will be communicated to residents as soon as they have been finalised.
The Council has been aware for some time that the gas pipework in both towers is ageing and has been considering various options for replacement along with substantial refurbishment of the towers. However, SGN has made it clear the situation must now be resolved urgently.
Cllr Natalie Thomas, Cabinet Member for Safer Homes, Homelessness and Housing Services, said:
“I understand that this situation will be worrying for residents. I have been informed that the Council has known for some time that the pipework is ageing, and I have requested a review to understand why this issue was not dealt with sooner. Residents deserve clear answers, as well as clear information about the options being considered for their homes.”
The Building Safety Regulator, Fire Brigade and Regulator of Social Housing have been informed of the situation, and we will be keeping them up to date.
Residents can ask questions and discuss the plans with Council and SGN representatives on Tuesday 24 November, 6-7pm, at the 2000 Community Action Centre, 199-201 Grove Street, SE8 3PG.
For enquiries, email buildingsafety@lewisham.gov.uk or call 0800 028 2028. Anyone smelling gas should call 0800 111 999 immediately.